Data center moratorium request
Summary
The council put off its data center discussion to April 6 while an engineer studies the site. Resident Whitney Carson pressed the mayor on when he knew about the Prologis agreement, reigniting transparency concerns raised by Councilwoman Means-Davis.
At a glance
- Total mentions
- 8
- Last 30 days
- 0
Last discussed Jul 6, 2026.
Impact analysis
No direct cost to residents yet, though the city is paying for an independent engineering review.
Residents get more time to review and question the project before any council decision.
Any prospective data center developer would be delayed by a moratorium.
Mentions & discussions (8)
City Council - Jul 6, 2026
Resident Connie Lindsay asked the council for a one-year moratorium on data centers, citing electricity and water consumption, tax abatements, and petitions with nearly 1,000 signatures. Council members stayed silent on advice of litigation counsel.
City Council - Jun 17, 2026
Residents have repeatedly asked the council to pause data center development for further study, citing environmental, utility-rate, water and property-value concerns. The council says it can't comment due to active litigation; residents argue a zoning moratorium is separate.
City Council - Jun 1, 2026
A resident who traveled from New York City demanded answers on the data center, citing a 9,000-signature petition against the annexation and asking if residents could vote on it or whether council members benefited financially. The mayor said litigation prevents comment; Councilman Reed denied receiving funds, and Councilwoman Sanders made a pointed remark referencing $7 million.
City Council - May 4, 2026
Residents keep pressing the city on data centers. Connie Lindsay asked whether any developer has approached the city about a data center, battery storage, or solar farm, and whether any NDAs have been signed since ProLogis — officials said no. David Sly read a lengthy 'cease and desist' notice into the record.
City Council - Apr 20, 2026
A petition signed by roughly 2,500 residents asks the council to pause data center development for a year while it studies noise, setbacks, and zoning standards. The county has already paused data centers; the council took no action Monday.
City Council - Mar 23, 2026
Residents handed over petitions from city voters asking for a six-month moratorium on data center development. No council member would make a motion on it.
City Council - Feb 18, 2026
Residents are pressing the council to reconsider its denial of a data center moratorium while the city drafts a development ordinance. Thompson also opposed development behind the Circle K on SR 44 because two-lane roads can't handle the traffic.
City Council - Feb 2, 2026
The council put off its data center discussion to April 6 while an engineer studies the site. Resident Whitney Carson pressed the mayor on when he knew about the Prologis agreement, reigniting transparency concerns raised by Councilwoman Means-Davis.
Related development
Prologis data center annexation (Ordinance No. 26-3052)
Residents fear the project will bring noise, light, water, and electric impacts, and want protections locked in before the annexation vote.
Data Center / Prologis Property Proposal
If approved, the project could bring major development to the site, but drainage, geology, and utility capacity questions are still being studied.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Shelbyville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.