High PriorityRoadsopen

Bridge 9 property purchase

Summary

The Cavehill Bridge replacement is now pegged at roughly $900,000 including permits, surveys, land and concrete. A federal funding lead through Rep. Erin Houchin's office could save the county's bridge fund.

At a glance

Total mentions
8
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Nov 9, 2026.

Impact analysis

💰Financial impact

About $900,000 total, with possible federal help to avoid draining the bridge fund.

✅Who benefits

Residents who use the Cavehill crossing and travelers on that route.

⚠️Who could be affected

Anyone who has detoured around the closed bridge in the meantime.

Mentions & discussions (8)

MeetingNov 9, 2026

Ripley County Government Commissioners — November 9, 2026

The county is buying land for the new bridge at Cavill for $26,034.23, with all owners in agreement and a screening-planting request accommodated.

MeetingOct 8, 2026tabled

Ripley County Government Commissioners Meeting Part 2 — October 8, 2026

The county is hiring contractors for concrete and crane work on Bridge 9. Bids came in but several lacked required bid bonds, so the board held off picking a contractor until its attorney reviews the submissions.

MeetingAug 31, 2026

Ripley County Government Commissioners — August 31, 2026

The bid notice for bridge 9 will be advertised next week, with bids opened in October.

MeetingJul 20, 2026

Ripley County Government Council — July 20, 2026

The highway department got $26,030 to buy the land where Bridge 9 will be rebuilt, plus $28,357 to match a Community Crossings road grant.

MeetingJul 6, 2026approved

Ripley County Government Commissioners — July 6, 2026

Hydraulic reports mean the new bridge must be nine feet longer overall (three feet per end) to stay above high water, pushing abutments further into adjacent fields.

MeetingMay 11, 2026

Ripley County Government Commissioners — May 11, 2026

The long-awaited Bridge 9 project is nearly ready — property purchase is the last hurdle. It'll cost about $1 million in county funds and will cut next year's chip and seal program from 210 miles to 80 miles.

MeetingMar 30, 2026

Ripley County Government Commissioners — March 30, 2026

Bridge 9 work will start by March 27, 2027, with concrete curing pushing completion to around March of next year. Landowners along the route are reportedly happy with the new bridge.

MeetingJan 15, 2026

Ripley County Government Commissioners — January 15, 2026

The Cavehill Bridge replacement is now pegged at roughly $900,000 including permits, surveys, land and concrete. A federal funding lead through Rep. Erin Houchin's office could save the county's bridge fund.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Ripley County

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.