Aging county bridges
Concrete barrier work at Crisman Road over Portage Avenue and INDOT Rural-Aid applications to replace two rural bridges could improve safety on county roads.
NIPSCO superload haul route through county roads
Commissioners denied a revised route that would move enormous data-center transformers over 7.43 miles of small, chip-and-sealed county roads. They argued the railroad, the state, and NIPSCO all refused to bear the weight or cost, leaving Porter County as the 'path of least resistance' with only a $7 million bond as protection — one that could vanish before hidden road damage appears.
Shared driveway capacity and maintenance for six parcels
Six properties share a single driveway off US 6, including the new tree business, a septic/excavation business, and several homes. Members questioned whether the drive can handle heavy equipment, two-way traffic, and emergency vehicles, and who pays for repairs.
Traffic and roadway impacts on US 6 and Calumet Avenue
Longtime resident Todd Matnich says stormwater from the intersection already ponds over his septic field and runs within 30 feet of his well, and he fears more pavement will make it worse. The project engineer testified the site drains north to an agricultural field and that detention will be provided, but the full drainage review comes at the development plan stage.
Parade of Homes road closure of Farm View Drive
St. Iakovos church's first 5K hit a snag — organizers hadn't notified residents or coordinated with the sheriff. The commissioners tabled it and pointed them to the county's process so neighbors aren't surprised by the October 24 closure.
State road funding shortfall
The governor's gas tax suspension could cost the county over $1 million in the next three months. The highway department may cut or delay projects this fall unless the state makes counties whole.
CR 100 S Road Safety Project Extended Closure
CR 100 S will close up to 70 days starting late July for a $5.4 million safety project removing hidden-driveway hills near Lakes of the Four Seasons. Detour via County Line Road; reopening expected in two construction seasons.
Senior and disability transportation funding
PCACS's ride program got a $20,000 raise to $100,000 after reporting 100+ denied trips per month and doubled fuel costs. This is how many seniors and veterans actually get to doctor visits.
Hackney Lane pavement and drainage improvements
The Hidden Hollow subdivision gets full-depth pavement reconstruction plus drainage fixes; bidding was authorized with bids opening May 12.
2026 road funding and Highway staffing
More than $6.5 million in new highway appropriations plus five new hires — this is the money that keeps county roads resurfaced, salted and maintained, and backfills staff shifted to Storm Water and the Bridge Crew.