Target Development INDOT covenant
Summary
INDOT wants a potential double turning lane into the Target site, but city engineers say traffic will never reach the trigger threshold in ten years. The city agreed to a covenant so INDOT will issue the permit.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Sep 8, 2026.
Impact analysis
Potential future cost if the traffic threshold is ever met, which engineers consider unlikely.
The Target Development project, which gains its INDOT permit.
Future administrations inherit a ten-year obligation, though engineers consider it unlikely to trigger.