Summary

The sewer board hired an engineering and design team for the big plant campus modernization project — Clark Dietz as lead engineers, TowerPinkster on architecture, plus surveying and geotechnical testing. Work starts this month and includes road and sidewalk improvements at the plant's main entrance.

At a glance

Total mentions
1
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 8, 2026.

Impact analysis

💰Financial impact

The initial contracts total about $67,200 combined, with the Clark Dietz master agreement capped at not-to-exceed amounts set per task order.

✅Who benefits

Residents benefit from modernized sewer plant facilities and improved pedestrian and road access at the plant entrance.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for New Albany

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.