Summary
Three bids were opened for resurfacing four roads across the county — 12B, 14B, 15th and Muckshaw — with the low total around $1.24 million. Awards should come at a future meeting once reviewed.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 2, 2026.
Impact analysis
Roughly $1.24 million to $1.48 million depending on which bid is awarded.
Drivers on those four road corridors get smoother, safer surfaces.
Donnie Brook area residents whose project was cut.
Mentions & discussions (4)
Marshall County Commissioner — November 2, 2026
The county got $445,794 in state matching funds for three road projects — E. 3rd Road, Linden Road, and 16th Road — with a county match of $89,158. Donnie Brook was dropped from the plan because only awarded projects move forward.
Marshall County Commissioner — August 17, 2026
The state grant program opens September 1 with a $1 million cap and an 80/20 match. Highway staff is eyeing 3rd Road to S.R. 331, 11th Road to Gumwood Road, and 11B Road south of US 30 — with US 30 interchange changes factoring into which gets picked.
Marshall County Commissioner — April 6, 2026
Three bids were opened for resurfacing four roads across the county — 12B, 14B, 15th and Muckshaw — with the low total around $1.24 million. Awards should come at a future meeting once reviewed.
Marshall County Commissioner — March 16, 2026
Four road projects — 14B, 12B, Muckshaw, and 15th Road — go out to bid March 23, with awards expected April 6 pending INDOT funding sign-off.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Marshall County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.