Longspur Battery Energy Storage System extension
Description
A 12-month extension of the BESS special exception was granted after the project attorney explained he missed the renewal deadline due to personal circumstances; four neighbors objected.
Impact summary
The project stays alive for another year, but the developer is on the clock to obtain permits or risk needing another extension the board may not grant.
Applicant
- Name
- Eagle Rock Land Company, LLC (owner); Longspur Energy Storage, LLC (petitioner)
- Address
- 4239 E. 181st Avenue (State Road 2), Eagle Creek Township
At a glance
- Hearings
- 1
- Public comments
- 0
- Total mentions
- 1
Last vote · Lake County Board of Zoning Appeals
Last discussed Apr 15, 2026.
Meeting timeline (1)
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Lake County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.