Deteriorated street concrete found during construction added $35,563 to the neighborhood patching project, now at $233,032.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Sep 15, 2026.
Impact analysis
Contract total rises 18 percent, from $197,469 to $233,032.
Treece Meadows residents get more complete street and driveway repairs.
Mentions & discussions (2)
Board of Works (Regular) - Sep 15, 2026
Deteriorated street concrete found during construction added $35,563 to the neighborhood patching project, now at $233,032.
Board of Works (Regular) - Jun 30, 2026
Three bids opened ranging from $197,469 to $472,329. The low bid came from Dixon Construction, but the board held off awarding pending review.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.