Sewer Projects Completed Under Budget
Summary
Two Lafayette Renew projects — the Prairie Oaks permanent bypass and the 2025 sanitary sewer rehab — wrapped up with small deductions instead of overruns, though the Prairie Oaks schedule slipped 243 days due to material delays and wet weather.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
Combined deductions of $17,119 across the two sewer contracts.
Utility customers benefit from completed sewer infrastructure delivered under budget.