Sewer Projects Completed Under Budget

Summary

Two Lafayette Renew projects — the Prairie Oaks permanent bypass and the 2025 sanitary sewer rehab — wrapped up with small deductions instead of overruns, though the Prairie Oaks schedule slipped 243 days due to material delays and wet weather.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.

Impact analysis

💰Financial impact

Combined deductions of $17,119 across the two sewer contracts.

✅Who benefits

Utility customers benefit from completed sewer infrastructure delivered under budget.