Poland Hill Road Improvements
Summary
A future project to rebuild Poland Hill Road from Beck Lane to Teal Road, with a new roundabout at Beck Lane, new pedestrian facilities, and an improved railroad crossing. Timing hasn't been set yet.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Mar 26, 2026.
Impact analysis
Not yet estimated; included among projects with a combined estimated cost of about $9.5 million in the declaratory resolution.
Residents and commuters on the southeast side get safer road, pedestrian, and railroad infrastructure once it's built.
Mentions & discussions (3)
Redevelopment Commission (Regular) - Mar 26, 2026
The TIF plan now includes rebuilding Poland Hill Road from Beck Lane to Teal Road, with a new roundabout at Beck Lane, new pedestrian facilities and an improved railroad crossing — but only after 9th Street is finished.
Redevelopment Commission (Regular) - Feb 26, 2026
A $562,839 design amendment lets the city rebuild Poland Hill Road from Beck Lane to Teal Road as one project in summer 2028, avoiding two simultaneous south-side road closures alongside the South 9th Street work.
Redevelopment Commission (Regular) - Jan 22, 2026
A future project to rebuild Poland Hill Road from Beck Lane to Teal Road, with a new roundabout at Beck Lane, new pedestrian facilities, and an improved railroad crossing. Timing hasn't been set yet.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.