Lead Service Line Replacement, Phase II
Summary
Material shortages added about three months to the lead service line replacement project, pushing completion to April 2026 and requiring an amendment to keep Wessler Engineering on the job.
At a glance
- Total mentions
- 9
- Last 30 days
- 0
Last discussed Aug 18, 2026.
Impact analysis
Contract budget was stretched through the end of 2025; amendment extends the engineering contract to project completion in April 2026.
Residents whose lead service lines get replaced with modern water service lines.
Residents awaiting service line replacement face a longer wait due to material delays.
Mentions & discussions (9)
Board of Works (Regular) - Aug 18, 2026
Phase I of the city's lead pipe replacement work is officially wrapped up, with the contractor paid in full. Old lead water lines around Lafayette have been replaced, and the warranty on that work runs through April 2027.
Board of Works (Regular) - Jul 14, 2026
Lafayette is moving into Phase II of replacing lead water service lines, with a nearly $15 million contract with Atlas Excavating and work starting right away. This matters for residents concerned about lead in drinking water and for neighborhoods that may see construction activity.
Board of Works (Regular) - Jun 30, 2026
The city is committing nearly $15 million to keep digging up lead water lines, but only has about $11 million in hand right now. Work will be invoiced only as funds allow, and the city may seek more money later. Low right-of-entry sign-ups limited how much Phase I money got spent.
Board of Works (Regular) - Jun 23, 2026
The next phase of the city's lead service line replacement work stayed on hold under advisement. Residents on old lead lines are still waiting for the Phase II work to move forward.
Board of Works (Regular) - Jun 16, 2026
The city is replacing lead water service lines across neighborhoods — a major public health and infrastructure effort. Phase I is now wrapping up with a final change order that came in $1 million under, and Phase II bids are still pending a Board decision.
Board of Works (Regular) - Jun 9, 2026
The city is replacing lead water service lines, with a bid of roughly $15 million from Atlas Excavating being funded by $5 million in grant money and a $5 million 0% interest loan from the Indiana State Revolving Fund. The award is on hold until the bond closing on June 18.
Board of Works (Regular) - Jun 2, 2026
Lafayette is replacing lead water service lines across the city, a nearly $15 million construction project. The city has $10 million committed — half in grant money and half as a 0% state loan — so grants cover the rest.
Board of Works (Regular) - May 26, 2026
Bids for the second phase of lead service line replacements — with a base bid around $15 million — remain under advisement while the board reviews them.
Board of Works (Regular) - Jan 13, 2026
Material shortages added about three months to the lead service line replacement project, pushing completion to April 2026 and requiring an amendment to keep Wessler Engineering on the job.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Lafayette
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.