High PriorityWater Utilitiesopen

Terrace Drive Sanitary Sewer Project final assessments

Summary

Residents on the 3200 block of Terrace Drive will get city sewer service so they can abandon their septic systems, through a Barrett Law assessment project.

At a glance

Total mentions
6
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Nov 4, 2026.

Impact analysis

๐Ÿ’ฐFinancial impact

Terrace Drive property owners will bear project costs through Barrett Law assessments.

โœ…Who benefits

Terrace Drive residents currently on septic systems.

โš ๏ธWho could be affected

Owners along the extension who will owe final assessments.

Mentions & discussions (6)

MeetingNov 4, 2026approved

Board of Works โ€” November 4, 2026

The Terrace Drive sewer project is complete and the city is setting a December 2 public hearing on the final Barrett Law assessments charged to affected property owners.

MeetingSep 16, 2026approved

Board of Works โ€” September 16, 2026

The sewer extension project hit its first pay milestone โ€” $102,897.60 to Dykman Excavating for work through August 31. The project keeps expanding sewer service on Terrace Drive.

MeetingJul 1, 2026approved

Board of Works โ€” July 1, 2026

About eight homes on Terrace Drive would gain access to city sanitary sewer. Property owners must sign a petition obligating them to pay roughly $6,000 and connect within about 90 days, with some flexibility at the board's discretion. One resident raised concerns about out-of-pocket grinder pump costs with no assistance program available.

MeetingMay 27, 2026discussed

Board of Works โ€” May 27, 2026

The city is extending sanitary sewer in the Terrace Tribe area and received four contractor bids ranging from about $232,000 to $523,000. The board held the bids under advisement rather than awarding a contract right away.

MeetingMar 25, 2026approved

Board of Works โ€” March 25, 2026

Residents on the 3200 block of Terrace Drive will get city sewer service so they can abandon their septic systems, through a Barrett Law assessment project.

MeetingFeb 11, 2026approved

Board of Works โ€” February 11, 2026

The sewer extension project is finished and paid for; now property owners along the route will get their final assessment notices, with a public hearing set for March 4, 2026.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Kokomo

What the council decided, in plain English โ€” one email a week.

Free. Unsubscribe with one click any time. We never sell your email.