Northside Interceptor Improvements Project
Summary
The big sewer project continues — the contractor Atlas Excavating billed $1.6 million for work through March. This keeps the city's sewer infrastructure upgrades on track.
At a glance
- Total mentions
- 11
- Last 30 days
- 1
Discussed at 2 meetings in the last 60 days; most recently Oct 28, 2026.
Impact analysis
$1,604,764.59 this pay application, with retainage now at $71,315.68.
Residents and businesses relying on the city's sewer system.
Mentions & discussions (11)
Board of Works — October 28, 2026
Another big payment on the sewer interceptor project — $224,573 to Atlas Excavating. Ongoing sewer infrastructure investment.
Board of Works — September 23, 2026
Work continues on the North Side Interceptor sewer improvement, with a $574,096 payment approved to contractor Atlas Excavating for work done through August 31.
Board of Works — August 19, 2026
Another $417,639.71 went to Atlas Excaving for sewer interceptor work — part of the city's ongoing wastewater infrastructure investment.
Board of Works — July 22, 2026
The sewer interceptor project advanced with a $382,872.89 progress payment to Atlas Excavating for work through June 30.
Board of Works — July 8, 2026
The board approved another contractor payment — about $303,000 — for the Northside Interceptor sewer work, keeping the major infrastructure project moving.
Board of Works — June 24, 2026
A $249,500 final pay application was approved for storm sewer work completed by Coomler Contracting.
Board of Works — May 6, 2026
The city will reimburse Duke Energy $135,488.65 for moving power lines to make way for the North Side Interceptor sewer project.
Board of Works — April 29, 2026
The board approved an amended $354,194 pay application for the Northside Interceptor, correcting an earlier erroneous request.
Board of Works — April 15, 2026
The big sewer project continues — the contractor Atlas Excavating billed $1.6 million for work through March. This keeps the city's sewer infrastructure upgrades on track.
Board of Works — February 18, 2026
The board approved the first contractor payment of $584,257.67 to Atlas Excavating for work completed through January 31, 2026, on this sewer infrastructure project.
Board of Works — January 14, 2026
The city's biggest infrastructure project on the docket — a $23 million sewer interceptor — officially got the green light to start construction now that bond funding is secured.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Kokomo
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.