Northside Interceptor Improvements Project

Summary

The big sewer project continues — the contractor Atlas Excavating billed $1.6 million for work through March. This keeps the city's sewer infrastructure upgrades on track.

At a glance

Total mentions
11
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Oct 28, 2026.

Impact analysis

💰Financial impact

$1,604,764.59 this pay application, with retainage now at $71,315.68.

✅Who benefits

Residents and businesses relying on the city's sewer system.

Mentions & discussions (11)

MeetingOct 28, 2026approved

Board of Works — October 28, 2026

Another big payment on the sewer interceptor project — $224,573 to Atlas Excavating. Ongoing sewer infrastructure investment.

MeetingSep 23, 2026approved

Board of Works — September 23, 2026

Work continues on the North Side Interceptor sewer improvement, with a $574,096 payment approved to contractor Atlas Excavating for work done through August 31.

MeetingAug 19, 2026approved

Board of Works — August 19, 2026

Another $417,639.71 went to Atlas Excaving for sewer interceptor work — part of the city's ongoing wastewater infrastructure investment.

MeetingJul 22, 2026approved

Board of Works — July 22, 2026

The sewer interceptor project advanced with a $382,872.89 progress payment to Atlas Excavating for work through June 30.

MeetingJul 8, 2026discussed

Board of Works — July 8, 2026

The board approved another contractor payment — about $303,000 — for the Northside Interceptor sewer work, keeping the major infrastructure project moving.

MeetingJun 24, 2026approved

Board of Works — June 24, 2026

A $249,500 final pay application was approved for storm sewer work completed by Coomler Contracting.

MeetingMay 6, 2026approved

Board of Works — May 6, 2026

The city will reimburse Duke Energy $135,488.65 for moving power lines to make way for the North Side Interceptor sewer project.

MeetingApr 29, 2026approved

Board of Works — April 29, 2026

The board approved an amended $354,194 pay application for the Northside Interceptor, correcting an earlier erroneous request.

MeetingApr 15, 2026approved

Board of Works — April 15, 2026

The big sewer project continues — the contractor Atlas Excavating billed $1.6 million for work through March. This keeps the city's sewer infrastructure upgrades on track.

MeetingFeb 18, 2026approved

Board of Works — February 18, 2026

The board approved the first contractor payment of $584,257.67 to Atlas Excavating for work completed through January 31, 2026, on this sewer infrastructure project.

MeetingJan 14, 2026approved

Board of Works — January 14, 2026

The city's biggest infrastructure project on the docket — a $23 million sewer interceptor — officially got the green light to start construction now that bond funding is secured.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Kokomo

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.