High PriorityDevelopmentopen

Kokomo Conference Center construction payments

Summary

The board approved a bundle of change orders adding $241,876.79 to the conference center project, plus nearly $2 million in contractor and professional payments. This keeps the project moving but adds to its overall cost.

At a glance

Total mentions
12
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Oct 21, 2026.

Impact analysis

💰Financial impact

Adds $241,876.79 in change orders and roughly $1.94 million in payments to the conference center project.

✅Who benefits

The city's convention and visitors economy benefits as the conference center construction advances toward completion.

Mentions & discussions (12)

MeetingOct 21, 2026approved

Board of Works — October 21, 2026

The board approved three payments for the Conference Center project, including contractor pay for tech and low-voltage systems and interior signage. It's a routine step in finishing the downtown venue.

MeetingOct 7, 2026approved

Board of Works — October 7, 2026

The conference center project hit another milestone with a $1.73 million pay application — though the contractor only got a partial retainage release of about $1.4 million rather than the full amount requested.

MeetingJul 29, 2026approved

Board of Works — July 29, 2026

The board moved nearly $530,000 to Hagerman Construction for conference center work, keeping some in retainage to make sure the job gets finished right. Another invoice went to Global Industrial for the same project.

MeetingJun 24, 2026approved

Board of Works — June 24, 2026

Millions in ongoing conference center costs — including an $835,736 Hagerman pay app — plus net-zero change orders got final approval.

MeetingMay 27, 2026approved

Board of Works — May 27, 2026

The board approved roughly $753,000 in conference center pay applications plus nine change orders at zero net cost, keeping the project on budget and schedule.

MeetingMay 13, 2026approved

Board of Works — May 13, 2026

The board paid three invoices for the conference center — site lining, kitchen equipment down payment and a scissor lift — after CVB review.

MeetingMay 6, 2026approved

Board of Works — May 6, 2026

The board approved five change orders with no net cost increase plus Pay App No. 22 for $839,020.50 to the conference center contractor.

MeetingApr 29, 2026approved

Board of Works — April 29, 2026

The CVB approved a $21,357.88 payment to Clifford Signs for interior signage at the conference center project.

MeetingMar 25, 2026approved

Board of Works — March 25, 2026

The board approved another $45,710 in change orders plus roughly $893,000 in contractor and consultant invoices for the conference center project.

MeetingFeb 25, 2026approved

Board of Works — February 25, 2026

The board approved a bundle of change orders adding $241,876.79 to the conference center project, plus nearly $2 million in contractor and professional payments. This keeps the project moving but adds to its overall cost.

MeetingFeb 11, 2026approved

Board of Works — February 11, 2026

The board approved seven change orders totaling nearly $193,000 for the conference center construction project, on the recommendation of the city's owner's representative and the CVB.

MeetingJan 28, 2026approved

Board of Works — January 28, 2026

The conference center project moved forward with nearly $980,000 in approved pay applications, including over $829,000 to general contractor Hagerman.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Kokomo

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.