Fire Station No. 6 reconstruction
Summary
The board approved the latest contractor payment and two small change orders to finish the rebuilt fire station, covering roofing, plumbing, HVAC, electrical and interior work. Fire service response depends on getting this facility back online.
At a glance
- Total mentions
- 10
- Last 30 days
- 1
Discussed at 2 meetings in the last 60 days; most recently Nov 18, 2026.
Impact analysis
Over $460,000 moved this round, with the pay application's $437,681.63 the largest single item.
Firefighters and the residents they serve get a completed, modern fire station.
Mentions & discussions (10)
Board of Works — November 18, 2026
The board approved the latest contractor payment and two small change orders to finish the rebuilt fire station, covering roofing, plumbing, HVAC, electrical and interior work. Fire service response depends on getting this facility back online.
Board of Works — October 7, 2026
Construction on the rebuilt fire station is moving along — stone, brick, drywall, plumbing, HVAC and electrical work is in — with a $355,684 payment approved to keep the project moving.
Board of Works — August 12, 2026
The city's new fire station keeps moving forward, with another $671K paid out for masonry, walls, plumbing, HVAC and electrical work.
Board of Works — July 22, 2026
The rebuild of fire station #6 hit another construction milestone, with the board approving a $392,290.50 progress payment. Work completed includes walls, stairs, drywall, plumbing, HVAC, and electrical.
Common Council — June 10, 2026
The rebuild of Kokomo's Fire Station No. 6 continues, with the board approving its tenth progress payment of nearly $856,000. The work so far includes foundations, walls, roofing, and building systems.
Board of Works — May 13, 2026
The city's new fire station hit another construction milestone, with the board approving nearly $630,000 for completed work like walls, roofing and electrical.
Board of Works — April 15, 2026
The rebuilt Fire Station 6 is moving along — walls, roofing, and electrical work are in, and the contractor got paid $495,934 for the latest phase.
Board of Works — April 8, 2026
The city hired SME to monitor construction and the vapor intrusion system at the new fire station. This keeps the project on track and protects air quality at the site.
Board of Works — March 11, 2026
The city's fire station rebuild hit another milestone with steel, walls, and plumbing work now paid for — over $863K in new payments approved. The project keeps moving toward completion.
Board of Works — January 14, 2026
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Kokomo
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.