Fire Station No. 6 reconstruction

Summary

The board approved the latest contractor payment and two small change orders to finish the rebuilt fire station, covering roofing, plumbing, HVAC, electrical and interior work. Fire service response depends on getting this facility back online.

At a glance

Total mentions
10
Last 30 days
1

Discussed at 2 meetings in the last 60 days; most recently Nov 18, 2026.

Impact analysis

💰Financial impact

Over $460,000 moved this round, with the pay application's $437,681.63 the largest single item.

✅Who benefits

Firefighters and the residents they serve get a completed, modern fire station.

Mentions & discussions (10)

MeetingNov 18, 2026approved

Board of Works — November 18, 2026

The board approved the latest contractor payment and two small change orders to finish the rebuilt fire station, covering roofing, plumbing, HVAC, electrical and interior work. Fire service response depends on getting this facility back online.

MeetingOct 7, 2026approved

Board of Works — October 7, 2026

Construction on the rebuilt fire station is moving along — stone, brick, drywall, plumbing, HVAC and electrical work is in — with a $355,684 payment approved to keep the project moving.

MeetingAug 12, 2026approved

Board of Works — August 12, 2026

The city's new fire station keeps moving forward, with another $671K paid out for masonry, walls, plumbing, HVAC and electrical work.

MeetingJul 22, 2026approved

Board of Works — July 22, 2026

The rebuild of fire station #6 hit another construction milestone, with the board approving a $392,290.50 progress payment. Work completed includes walls, stairs, drywall, plumbing, HVAC, and electrical.

MeetingJun 10, 2026approved

Common Council — June 10, 2026

The rebuild of Kokomo's Fire Station No. 6 continues, with the board approving its tenth progress payment of nearly $856,000. The work so far includes foundations, walls, roofing, and building systems.

MeetingMay 13, 2026approved

Board of Works — May 13, 2026

The city's new fire station hit another construction milestone, with the board approving nearly $630,000 for completed work like walls, roofing and electrical.

MeetingApr 15, 2026approved

Board of Works — April 15, 2026

The rebuilt Fire Station 6 is moving along — walls, roofing, and electrical work are in, and the contractor got paid $495,934 for the latest phase.

MeetingApr 8, 2026approved

Board of Works — April 8, 2026

The city hired SME to monitor construction and the vapor intrusion system at the new fire station. This keeps the project on track and protects air quality at the site.

MeetingMar 11, 2026approved

Board of Works — March 11, 2026

The city's fire station rebuild hit another milestone with steel, walls, and plumbing work now paid for — over $863K in new payments approved. The project keeps moving toward completion.

MeetingJan 14, 2026approved

Board of Works — January 14, 2026

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Kokomo

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.