Summary

The council advanced six annexations and two industrial rezonings that clear the way for Digital Realty's proposed 476-acre, three-building data-center campus and a separate industrial-land area. Supporters tout an estimated $44 million annual tax revenue and thousands of construction jobs with no abatement; opponents fear farmland loss, water and power strain, generator noise and emissions, and weak enforceability of company promises. This was first reading only — final votes come later.

At a glance

Total mentions
4
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 26, 2026.

Impact analysis

💰Financial impact

Company representatives project $40-50 million a year in property tax revenue from a $1.5-2 billion investment, but residents questioned how much reaches schools and whether indirect costs could offset it.

✅Who benefits

If built, the city gains a major new tax base, IBEW tradespeople get years of local construction work, and landowners selling into the annexation benefit.

⚠️Who could be affected

Residents near the site face potential noise, generator emissions, well and water concerns, and loss of productive farmland; critics note the risk if the project is never completed.

Mentions & discussions (4)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Kokomo

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.