Medium PriorityParks Recopen

Cutler Park courts project

Summary

The board approved a $240,534 pay estimate plus a $35,750 modification for court posts, anchors and nets, and released nearly $22,500 in retainage to EMB Paving.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Aug 19, 2026.

Impact analysis

💰Financial impact

Payment of $240,534.35 plus a $35,750 modification; the contract now totals $690,063.95.

✅Who benefits

Park users and recreational players get new court facilities at Cutler Park.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Kokomo

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.