665-acre industrial rezone
Summary not yet generated for this topic.
Community sentiment
At a glance
- Public comments
- 20
- Last 30 days
- 0
Last discussed Feb 10, 2026.
Public comments (20)
Asked why the public wasn't notified years ago and argued the project will raise taxes and utilities and displace long-time residents.
Planning Commission — February 10, 2026 · 1:03:54 →Urged the commission to reject a possible data center, warning it would drain the town's electricity and water and make people sick.
Planning Commission — February 10, 2026 · 1:07:21 →Lifelong 500 North resident asked what happens to the four-generation family homes on 450 North if the rezone passes.
Planning Commission — February 10, 2026 · 1:10:00 →Third-generation homeowner opposed the rezoning, citing environmental studies, cemetery protection, school-bus traffic safety, property values, and the IEDC investigation; asked for denial or continuance.
Planning Commission — February 10, 2026 · 1:10:35 →Argued Kokomo should invest in small nuclear or thorium power plants and energy independence instead of selling farmland to big corporations.
Planning Commission — February 10, 2026 · 1:17:38 →Her home of 40 years sits across from the proposed site; she said she got only seven days' notice and asked why the land east of the site — with few homes — wasn't used instead, citing Samsung affiliates' environmental non-compliance.
Planning Commission — February 10, 2026 · 1:20:39 →Questioned why the city is rezoning county land, challenged Whitmore and Blackwell's owner status on Beacon, noted the LLC was formed in July 2025 and signed purchase agreements by September, and asked for denial or continuance.
Planning Commission — February 10, 2026 · 1:25:40 →Gary McNew's wife; said purchase agreements are pending due diligence and urged the board to slow down, citing 70 years in the area and fears of expanding industrial growth.
Planning Commission — February 10, 2026 · 1:41:00 →Lives two miles outside the zone and said she wasn't notified; warned of utility bill spikes, loss of farmland and lack of information about what will actually be built.
Planning Commission — February 10, 2026 · 1:49:46 →Argued rezoning without a defined project is irresponsible, calculated that each Samsung job has cost taxpayers about $133,000 against $70,000 wages, and asked for a continuance.
Planning Commission — February 10, 2026 · 1:53:05 →Lifelong resident near the Amish community asked about traffic safety for Amish travelers, water and wells over the creek, empty industrial sites, and asked for an unfavorable vote.
Planning Commission — February 10, 2026 · 1:58:05 →Opposed the plan, citing $100 million in taxpayer incentives, rising costs of living, contaminated former sites like Continental Steel, and threats to fertile soil and the Wildcat watershed.
Planning Commission — February 10, 2026 · 2:10:47 →Said the nearest fire stations are too small or too far to serve a large industrial plant and urged fire protection be addressed first.
Planning Commission — February 10, 2026 · 2:15:48 →New resident noted 28 counties including this one were just declared a drought disaster area and questioned where water and power for the industrial park would come from.
Planning Commission — February 10, 2026 · 2:19:42 →Doesn't live in the area but has friends and family there who oppose it; asked the board to take time, noting contract deadlines can be extended.
Planning Commission — February 10, 2026 · 2:22:42 →Stated simply she does not agree with the plan.
Planning Commission — February 10, 2026 · 2:23:57 →A materials engineer who runs an EPA-certified drinking water lab, she said 60-70% of drinking water comes from the Wildcat Creek, detailed groundwater contamination and NMP recycling at the battery plants, and urged protection of source-water areas.
Planning Commission — February 10, 2026 · 26:08 →Lives on the zone's edge; said he wouldn't have bought land recently had he known, and asked why ground inside the bypass isn't used first.
Planning Commission — February 10, 2026 · 2:29:39 →Argued utility 'capacity' claims are misleading under HB 1421, that SB 1 changes plus abatements will yield essentially zero property tax revenue, and requested a two-year data center moratorium if the rezone passes.
Planning Commission — February 10, 2026 · 2:31:28 →A farmer whose family sold ground near KTP1 explained how 1031 exchanges drove up land prices, assessments, property taxes and cash rents; asked that the south (IEDC) and north portions be rezoned separately and that inside-bypass land be used first.
Planning Commission — February 10, 2026 · 2:35:06 →