NIPSCO Schahfer project updates
Summary
Commissioners want NIPSCO to hold a public meeting for farmers and landowners about its big transmission tower project before planting season, after several landowners raised concerns.
At a glance
- Total mentions
- 5
- Last 30 days
- 0
Last discussed Sep 8, 2026.
Impact analysis
The county took roughly $15,000 in water damage at the Prosecutor's Office and is pricing battery backup.
Farmers and landowners along the NIPSCO route get answers before crews arrive.
Local industries and 6,000 residents lost power for 27 hours during the April outage.
Mentions & discussions (5)
Jasper County Commissioners — September 8, 2026
The CCGT project is on schedule with ongoing dump truck traffic and road repairs, while the gas peaker's online date has slipped to 2028. Traffic routing around 300 East remains a concern.
Jasper County Commissioners — May 4, 2026
After Rensselaer went dark for 27 hours during a labor dispute, the board president publicly called for a 'disaster clause' in NIPSCO-union contracts so local crews can restore power faster.
Jasper County Commissioners — March 2, 2026
NIPSCO's gas peaker project is on schedule, but commissioners and residents flagged serious traffic backups on US 231 and asked for better traffic management.
Jasper County Commissioners — February 17, 2026
Commissioners want NIPSCO to hold a public meeting for farmers and landowners about its big transmission tower project before planting season, after several landowners raised concerns.
Jasper County Commissioners — January 6, 2026
NIPSCO wants to rezone five parcels totaling roughly 3,200 acres at the Schaefer station for combined-cycle gas generation and possibly a data center. The Plan Commission recommended against it, but the commissioners have final say and are holding out for signed 'assurances' on water, traffic, property values and county revenue before deciding within weeks.
Related development
NIPSCO Schaefer I2 and Conservation rezone
The county locks in no data center or extra generation on the parcel forever; the conservation acreage could eventually offer public trails, birdwatching, and a river overlook.
NIPSCO Schaefer rezone — CCGT generation and potential data center
The project could bring billions in investment and jobs but raises resident concerns about groundwater, wells, noise, light pollution, traffic and property values near Wheatfield.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Jasper County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.