Bridge repairs on three county structures
Summary
The county approved design work with BF&S for replacing Bridge 88, including a possible box culvert and intersection realignment, with permitting likely pushing construction to fall 2027.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Sep 8, 2026.
Impact analysis
Box culvert alternative estimated around $1 million.
Residents and landowners who use that county road crossing.
None identified; landowners at the meeting were reported on board with the plan.
Mentions & discussions (3)
Jasper County Commissioners — September 8, 2026
Bids were opened to replace or repair Bridges 4, 68 and 261, with the low bid just under $1 million. The board is reviewing the bids before awarding.
Jasper County Commissioners — August 3, 2026
Three bridges get deck repairs this fall through competitive bids, and the county is eyeing Amazon economic impact money to replace the safety-problem Bridge 88 next year.
Jasper County Commissioners — February 2, 2026
The county approved design work with BF&S for replacing Bridge 88, including a possible box culvert and intersection realignment, with permitting likely pushing construction to fall 2027.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Jasper County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.