Data Center Rezoning Developer Commitment Amendments
Description
The board approved amending developer commitments to increase maximum structure height from 60 to 75 feet and extend the community enhancement agreement deadline to July 6, 2026.
Impact summary
Facilitates data center development design flexibility and provides adequate time for comprehensive community benefit negotiations.
Applicant
- Address
- NIPSCO-owned parcels
At a glance
- Hearings
- 1
- Public comments
- 0
- Total mentions
- 1
Last vote · County Commission
Last discussed Apr 6, 2026.