AWS Data Center — Improvement Location Permit
Description
The commissioners approved the improvement location permit for the AWS data center now that the final plat is recorded and BF&S has signed off; the road use agreement is still being finalized.
Impact summary
This is the biggest project in county history — years of construction traffic, hundreds of workers, and a permanent industrial campus — but also major economic impact funding for law enforcement and roads.
Applicant
- Name
- AWS / Ryan Companies
At a glance
- Hearings
- 2
- Public comments
- 0
- Total mentions
- 2
Last vote · County Commission
Last discussed Aug 17, 2026.
Meeting timeline (2)
Jasper County Commissioners — August 17, 2026
The commissioners approved the improvement location permit for the AWS data center now that the final plat is recorded and BF&S has signed off; the road use agreement is still being finalized.
Jasper County Commissioners — August 3, 2026
AWS wants a permit for phase two site work — 13 data center buildings and 3 ancillary buildings on 318 acres, with 76.3% lot coverage, 554 trees, dark-sky lighting, 20 stormwater basins and a riparian wetland area with future public trails. Commissioners continued the vote to August 17 pending the signed final plat.
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Jasper County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.