Bridge 48 Archaeological Cost Overrun
Summary
A dig on the CR 500 West bridge project turned up an archaeological site, forcing extra report and artifact work that wasn't in the original engineering contract. The county signed a supplemental agreement paying for it — though the site turned out not to be significant.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Apr 20, 2026.
Impact analysis
Added fees beyond the original Egis contract, exact amount not stated.
Motorists using CR 500 West, since the bridge project stays on track.