Pond lighting project completion
Summary
Donations are nearly at goal for lighting around the pond, with Duke Energy and REMC grants adding more. Locates must be done by April 27 or the boring contractor is lost.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jul 21, 2026.
Impact analysis
Mostly donation- and grant-funded; a $3,000-not-to-exceed locate contract and possible bollard, striping, and pavement work remain.
Everyone who walks the park after dark gets safer lighting and a better path.
Mentions & discussions (4)
Memorial Park Board - Jul 21, 2026
The pond lighting project is done and paid for, generating about $76,000 in donations from local foundations, Duke Energy, and individual pole sponsors.
Memorial Park Board - May 19, 2026
The park lighting project is on track for June completion — underground work and pole bases are done, with a roughly $40,000 invoice coming from the dedicated money-market fund.
Memorial Park Board - Apr 21, 2026
Donations are nearly at goal for lighting around the pond, with Duke Energy and REMC grants adding more. Locates must be done by April 27 or the boring contractor is lost.
Memorial Park Board - Feb 17, 2026
Eight lighted poles will line the walking path, paid almost entirely by community pole sponsorships. A local electrician's $68,500 bid was accepted after he shaved off $2,000.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Henry County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.