Medium PriorityRoadsopen

Highway projects and McCordsville overpass push

Summary

The McCordsville intersection bid date slipped from February to April, with payments expected after June. Board members asked for a firmer cost estimate of the county's share before the next meeting.

At a glance

Total mentions
8
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Sep 29, 2026.

Impact analysis

💰Financial impact

Unknown county share — members asked for an updated estimate.

✅Who benefits

Travelers through the McCordsville intersection once rebuilt.

⚠️Who could be affected

If the state redirects money, the interchange timeline and county budget could take the hit.

Mentions & discussions (8)

Greenfield IndianaOct 31, 2026

County, city to receive state road funding - The Daily Reporter

County, city to receive state road funding The Daily Reporter - Greenfield Indiana

MeetingSep 29, 2026

County Commissioners - Sep 29, 2026

The 300N/700W roundabout is open, and the county is chasing an 80% federal grant to overpass 500 West over State Road 67 to ease McCordsville traffic jams.

MeetingMay 14, 2026

Redevelopment Commission - May 14, 2026

600 West is wrapping up and the airport will maintain the Airport Blvd roundabout; utility work continues between 600 and 700 West. Budget season starts next month with a capital plan projecting RDC items like daycare, police and fire north of Amplify out to 2044.

MeetingMay 13, 2026

County Council (Regular) - May 13, 2026

Paving started, the 300 South Bridge opens by month's end, the county is buying the Jack & Sons downtown property for a bridge project with a $400,000 brownfield cleanup grant, and a fuel excise-tax suspension could squeeze the highway budget.

MeetingApr 9, 2026

Redevelopment Commission - Apr 9, 2026

Mark Witsman reported the McCordsville project is about to go out to bid, with an RDC funding request of roughly $3 million expected after June.

MeetingMar 12, 2026

Redevelopment Commission - Mar 12, 2026

The Broadway/600W intersection ($3.1 million) bids this summer, the 750N roundabout is in right-of-way, and a successful grant flipped 900N in for Aurora Way — with McCordsville reimbursing the RDC. The town is also floating a conceptual $11 million bridge over 500W to avoid an $80 million rail underpass and to fix deadly rail crossings.

MeetingMar 3, 2026

County Commissioners - Mar 3, 2026

Roundabout contract increase approved, two bridges reopen late spring, and commissioners must decide by April whether to keep funding HCSS senior/micro transit in 2027.

MeetingJan 8, 2026

Redevelopment Commission - Jan 8, 2026

The McCordsville intersection bid date slipped from February to April, with payments expected after June. Board members asked for a firmer cost estimate of the county's share before the next meeting.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Hancock County

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.