300 North construction and road hardening
Summary
The 300N road project is on schedule and on budget, with fiber and water line upgrades done. The main stretch finishes next year.
At a glance
- Total mentions
- 4
- Last 30 days
- 1
Discussed at 2 meetings in the last 60 days; most recently Nov 12, 2026.
Impact analysis
Within the approved project budget.
Commuters and freight traffic using 300N and the growing Mount Comfort corridor.
Residents and commuters using 300 North this fall will face traffic interruptions.
Mentions & discussions (4)
Redevelopment Commission - Nov 12, 2026
The 300N road project is on schedule and on budget, with fiber and water line upgrades done. The main stretch finishes next year.
Redevelopment Commission - Oct 8, 2026
The county will apply in November for a federal aid grant to build the next segment of 300N between 400W and 300W. Pool says the project is strong, matching money is available, and the county has a good track record with INDOT.
Redevelopment Commission - Jul 9, 2026
Drivers on 300 North will face interruptions this fall as utilities and concrete road hardening are installed. The hardening prevents the kind of collapse that happened on 700 West under detour traffic, and work will move to 500 North and 400 West soon.
Redevelopment Commission - Jan 8, 2026
The 300 North road widening project successfully let for bids, and the state and federal governments are helping cover $2 million of the cost — a big break for the county's budget.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Hancock County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.