Decennial data center $25M community impact payment

Summary

The mayor met with Decennial Group partners on the pending data center agreement and reiterated the city's June 30 deadline, saying any request to extend it should carry financial penalties.

At a glance

Total mentions
6
Last 30 days
0

Last discussed Jun 22, 2026.

Impact analysis

💰Financial impact

A major development agreement with a hard June 30 deadline — potentially a significant future investment.

✅Who benefits

Hammond residents if the data center project moves forward.

⚠️Who could be affected

None identified, though the Mayor acknowledged residents of comparable projects elsewhere have complained; Hobart's site draws no complaints.

Mentions & discussions (6)

MeetingJun 22, 2026

Hammond Common Council — 2026-06-22

The mayor told Councilman Kalwinski he's 'not super confident' the long-negotiated data center deal will close — no more extensions, and the contract dies June 30. The deal included community benefits like 20 years of College Bound funding.

MeetingJun 8, 2026approved

Hammond Common Council — 2026-06-08

The council added a $25 million up-front payment to Decennial's existing $80 million commitment. But the mayor warned the whole deal could be killed if Decennial misses its June 30 deadline — and said he won't extend it again.

MeetingMay 11, 2026

Hammond Common Council — 2026-05-11

The mayor met with Decennial Group partners on the pending data center agreement and reiterated the city's June 30 deadline, saying any request to extend it should carry financial penalties.

MeetingMar 9, 2026

Hammond Common Council — 2026-03-09

The city gave the CoreWeave data center project its third and final extension, through June 30. If the NIPSCO power agreement and CoreWeave lease aren't done by then, Mayor McDermott says the city walks away and pursues another data center tenant for the former coal plant site.

MeetingFeb 23, 2026

Hammond Common Council — 2026-02-23

The Mayor said the city will grant a final four-month extension so the developer can finish a NIPSCO power agreement and lease with CoreWeave. A pending state bill could return 1% of data center proceeds to host cities, so the delay might actually get Hammond a better deal. A resident warned CoreWeave's B+ credit rating and debt load make the promised payoff questionable.

MeetingFeb 9, 2026

Hammond Common Council — 2026-02-09

Hobart just closed a massive Amazon data center deal worth $45 million to that city. Hammond's own data center deal got extended to the end of February — if there's no positive news, the city can walk away and find another developer.

Related development

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Hammond

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.