ApprovedOther

The Project at 100 Digital Crossroads Drive

Description

The council approved the second amendment to the development agreement, extending the CoreWeave data center deadline to June 30 so the NIPSCO power agreement and lease can be finalized.

Impact summary

If the deal closes, the former coal plant site becomes a data center, potentially offsetting big revenue shortfalls the city is bracing for.

Applicant

Name
301 Digital Crossroads, LLC / Decennial Group, LLC / CoreWeave, Inc.
Address
100 Digital Crossroads Drive

At a glance

Hearings
1
Public comments
0
Total mentions
1

Last vote · Common Council

Approved9–0, unanimous

Last discussed Mar 9, 2026.