Lift station pump failure in Pines of Greenwood
Summary
A lift station pump in the Pines of Greenwood subdivision failed and can't be repaired — the station is running on its backup pump. A $24,536 replacement has a four-to-six-week lead time.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.
Impact analysis
The replacement pump costs $24,536, budgeted under station repair funds.
Pines of Greenwood residents avoid a sewage backup if the backup pump also fails.