Medium PriorityWater Utilitiesopen

Lift station pump failure in Pines of Greenwood

Summary

A lift station pump in the Pines of Greenwood subdivision failed and can't be repaired — the station is running on its backup pump. A $24,536 replacement has a four-to-six-week lead time.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Oct 5, 2026.

Impact analysis

💰Financial impact

The replacement pump costs $24,536, budgeted under station repair funds.

✅Who benefits

Pines of Greenwood residents avoid a sewage backup if the backup pump also fails.