Fifth pump added to Hurricane Creek lift station
Summary
The city awarded a $3.8 million contract to HIS Constructors to upgrade a sanitary sewer lift station — a behind-the-scenes project that keeps sewage flowing and prevents overflows into Hurricane Creek.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 19, 2026.
Impact analysis
$3,824,147 contract for the lift station upgrade.
Residents served by the sanitary sewer system, especially near Hurricane Creek, through improved sewer capacity.
Mentions & discussions (3)
Board of Public Works & Safety — October 19, 2026
A $685,756 change order adds a fifth pump, controls, and electronics to the sanitary lift station to handle sewage flow from developments expected to come to that area soon.
Board of Public Works — May 18, 2026
The city awarded a $3.8 million contract to HIS Constructors to upgrade a sanitary sewer lift station — a behind-the-scenes project that keeps sewage flowing and prevents overflows into Hurricane Creek.
Board of Public Works — March 16, 2026
All three construction bids came in defective and non-compliant under state law, so the lift station improvement project gets rebid — a delay for a project tied to the city's sewer pumping capacity.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenwood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.