The council gave final approval to a tax abatement for a $21 million, 280,000-square-foot industrial building at Graham Road and Main Street — expected to bring 15-30 jobs at $17-$20 an hour, with abatement savings passed through to a yet-unnamed tenant.
At a glance
- Total mentions
- 6
- Last 30 days
- 0
Discussed at 2 meetings in the last 60 days; most recently Oct 5, 2026.
Impact analysis
The city forgoes some property tax revenue during the abatement period in exchange for new investment and jobs.
Exeter/EQT, the prospective tenant, and workers who fill the new positions.
Southtech's new owner loses the abatement economics it counted on and must reapply.
Mentions & discussions (4)
Common Council — October 5, 2026
The council gave final approval to a tax abatement for a $21 million, 280,000-square-foot industrial building at Graham Road and Main Street — expected to bring 15-30 jobs at $17-$20 an hour, with abatement savings passed through to a yet-unnamed tenant.
Common Council — September 21, 2026
A developer is seeking a new $21 million tax abatement for a 280,000-square-foot industrial building at Grant and Main after the council rejected a prior abatement for the property earlier this year. A prospective tenant would take the whole building.
RDC — September 8, 2026
The new owner of the Graham & Main Street site is seeking abatement again after the old one was rescinded — this time for one 280,000-square-foot building with $21 million invested instead of the original two-building plan. Members pressed to make sure construction actually happens this time.
Common Council — July 6, 2026
The council showed it will judge abatement compliance case by case: one warehouse owner kept its abatement because ResMed signed a 12-year lease, while Southtech Land's abatement was terminated because the investment period expired with nothing built — though the new owner is now moving dirt and can reapply.
Related development
Exeter Southtech Land industrial building
Construction is expected by 2027 with the building fully assessed by 2028, adding major value to the east side TIF.
EQT Southtech Building 1 Tax Abatement
If approved, the abatement delays first tax assessment of the $21 million building to 2028 while supporting industrial leasing; savings pass to the tenant.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenwood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.