City Center Park Basketball Court Rebuild
Summary
The aging L-shaped courts at Northwest Park will be redesigned to try to fit two full courts instead of the current one and a half. The board approved $32,500 for design and bidding services; construction and demolition will come separately.
At a glance
- Total mentions
- 2
- Last 30 days
- 0
Last discussed Sep 1, 2026.
Impact analysis
$32,500 for design services; construction costs to come later.
Northwest Park neighbors and basketball players get modernized courts.
Some parking at the park will be blocked off during demolition since a quarter of the lot is needed for the work.
Mentions & discussions (2)
Parks Board — September 1, 2026
The aging L-shaped courts at Northwest Park will be redesigned to try to fit two full courts instead of the current one and a half. The board approved $32,500 for design and bidding services; construction and demolition will come separately.
Park Board — June 2, 2026
The old City Center Park basketball courts will be torn out after Labor Day and rebuilt under a $123,935 contract with All Star Paving, with construction carrying into next year. The delay keeps the busy summer season intact but means construction will overlap with next year's schedule.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenwood
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.