West Water Treatment Plant and Wellfield
Greenfield is moving ahead with a new water treatment plant at 823 West US 40 with an initial 6 million gallon per day capacity and four production wells. The board approved $739,000 for preliminary design, funded by TIF revenue the Redevelopment Commission set aside specifically for this project.
New water well site search after Well 15 delay
A property issue means the utility can't drill production Well 15 for at least three years while it works through National Park Service and DNR approvals. The board approved up to $120,000 for test wells on the Webb family property south of Beckenhorst Park and a $40,000 study of groundwater on the east side of the service territory.
Fairview and Thayer/Boyd stormwater rehabilitation
The city is asking the state for $750,000 to fix chronic flooding in the Fairview and Thayer/Boyd areas, kicking in $1.15 million of its own stormwater money. Winning a competitive grant depends partly on residents writing letters about their flooding experiences — the city needs two or three more.
WWTP Improvements Project Progress
Routine project bills were approved — Commonwealth Engineers' December services and Kleinpeter's final labor-standards invoice — plus a re-bid of the generator maintenance contract, where costs have climbed past an expected $10,000 a year.
100% TIF capture vs. pass-through to taxing units
Krohn walked through the annual illustration showing that capturing a $10 million development in TIF yields about $208,000 in new money, while passing it through to overlapping taxing units would only trim tax rates by a fraction of a cent. The commission again recommended capturing 100% of increment, and the auditor notification letter was approved.
South Street water main replacement
An award recommendation was on the agenda for replacing the water main along South Street — infrastructure that affects water service reliability for that corridor.
Water and wastewater rate increases
The council passed first reading of an ordinance raising water and sewer rates on a schedule over time. The public hearing is set for July 22 — after mailed notice to customers outside the city — so residents will have a formal chance to comment before any final vote.
Liberty Shores lift station emergency repair
Crews found a hole 'about the size of a football' in the lift station piping during routine inspections — the station serves a big chunk of the west side. The board approved a $27,180 emergency repair by Maddox Industrial Group, with work expected done by Friday. The station will eventually be taken offline by the new interceptor project.
Wastewater capacity constraints limiting northwest-side development
The sewer utility can't issue a will-serve letter for the Redwood Phase 2 area due to capacity limits, so permits are on hold even though the plan is approved. A $20 million pipeline down Meridian Street is in design to relieve downtown lines.
Weaning water and sewer utilities off TIF subsidies
The RDC's $500,000-a-year contributions to water and sewer bonds keep rates lower, but the utilities can't meet their bond coverage ratios without that help. With a $38 million water project and $25 million sewer interceptor looming, the city wants gradual rate increases over four years so the utilities can stand on their own before the big North TIF area sunsets in 2039.
PFAS litigation legal services
The city is considering a contract for outside legal help in PFAS (forever chemicals) class action litigation, likely tied to water utility contamination concerns.
Utility projects shifted off the RDC list
The Meridian Road sanitary sewer and Davis Road interceptor projects (new water plant ~$12M, wastewater extension ~$7M, electric building ~$5M) would move from TIF funding to the utilities, paid for by ratepayers through planned bonds instead.