The board approved engineering design work to grow the North water plant from 4 to 6 million gallons a day, using remaining State Revolving Fund loan money. It's the first step toward keeping enough water pressure and capacity as Greenfield keeps growing.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Jun 23, 2026.
Impact analysis
Funded with money left in the city's existing State Revolving Fund loan; engineering design costs come first, construction follows via the BOT contractor.
Every resident and business that depends on reliable water service as the city grows.
None directly; ratepayers could face increases, though the intent is to place costs on new development.
Mentions & discussions (4)
Board of Works (Work) - Jun 23, 2026
The city's sewers and the Potts Ditch lift station are at capacity, so new developments like Schaefer Farms can't connect. The Davis/Meridian BOT project bypasses downtown to free up room, saving roughly a year versus traditional bidding.
Plan Commission - May 12, 2026
The sewer utility can't issue a will-serve letter for the Redwood Phase 2 area due to capacity limits, so permits are on hold even though the plan is approved. A $20 million pipeline down Meridian Street is in design to relieve downtown lines.
City Council - Apr 22, 2026
The city is moving forward with a proposed new water treatment plant and wellfield on West U.S. 40, plus distribution system improvements, funded through the state Drinking Water State Revolving Fund loan program. This shapes water service and rates for years to come.
Board of Works - Feb 10, 2026
The board approved engineering design work to grow the North water plant from 4 to 6 million gallons a day, using remaining State Revolving Fund loan money. It's the first step toward keeping enough water pressure and capacity as Greenfield keeps growing.
Related development
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenfield
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.