Meridian and Davis Road Sanitary Sewer Improvements
Summary
The city's sewers downstream of the Potts Ditch lift station have almost no capacity left, which could block future development like the planned Shafer Farms subdivision. This project builds a new interceptor from Davis Road to New Road, eliminates two or three aging lift stations, and opens room to grow.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jul 14, 2026.
Impact analysis
Nearly $3.67 million for design and construction engineering, with construction likely bid in mid-2027 and possibly financed through the SRF.
Existing sewer customers, new development on the south and west side, and the future water plant's backwash flows.
Mentions & discussions (3)
Board of Works (Work) - Jul 14, 2026
A design bookkeeping fix: $48,500 in survey costs moved between task orders so the sewer project design can keep moving forward with no change in total cost.
Board of Works - Apr 28, 2026
The city's sewers downstream of the Potts Ditch lift station have almost no capacity left, which could block future development like the planned Shafer Farms subdivision. This project builds a new interceptor from Davis Road to New Road, eliminates two or three aging lift stations, and opens room to grow.
City Council - Apr 22, 2026
A presentation on a sewer interceptor project at Davis and Meridian roads was on the agenda — infrastructure that supports growth in that corridor.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greenfield
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.