Jail HVAC control system failure
Summary
The jail needs a new HVAC unit costing $64,900 from the correctional facilities fund. It was advertised for final approval at a later meeting.
At a glance
- Total mentions
- 5
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Nov 16, 2026.
Impact analysis
$64,900 from the correctional facilities fund.
Jail staff and inmates get a working climate system.
County taxpayers may face a sizable repair bill from the correctional facilities fund.
Mentions & discussions (5)
Greene County Council โ November 16, 2026
The jail needs a new HVAC unit costing $64,900 from the correctional facilities fund. It was advertised for final approval at a later meeting.
Greene County Council โ March 30, 2026
Broken HVAC controllers at the jail will be replaced for $64,900 so temperature control can be automated and centralized โ an issue for both inmates and staff.
Greene County Commissioners โ March 3, 2026
The jail is getting a new $64,900 HVAC control system, funded from the LIT Correctional Facilities Fund once Council signs off.
Greene County Council โ February 23, 2026
The jail's automated heating controls are wildly out of calibration โ readings off by up to 10 degrees โ forcing staff to manually balance hot water valves, especially dangerous during the cold snap. The county will spend $64,900 to replace the failed control system in the 2019 jail expansion, which must maintain required negative airflow.
Greene County Commissioners โ February 17, 2026
The jail's temperature controls are failing, forcing staff to adjust valves by hand and check temperatures with infrared guns. Fixing it could cost significant money, likely from the LIT Correctional Facilities Fund, and needs council approval.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Greene County
What the council decided, in plain English โ one email a week.
Free. Unsubscribe with one click any time. We never sell your email.