EDA water project delays
Summary
The federally funded water project serving the Westgate Technology Park hit snags — archaeological review, historic-site checks, and an Army Corps permitting question — pushing back the bid opening. The EDA also wants to fund a water tower in Daviess County.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 6, 2026.
Impact analysis
The grant brought $2.9 million into the local water system; delays don't cost money yet but compress the timeline.
Businesses at Westgate Technology Park and nearby residents who need more water capacity.