Worthington Solar Project — Battery Energy Storage System Amendment
Description
The company asked to amend its economic development agreement to add a battery energy storage component with $50 million in new investment, raising its annual payments to the county from $250,000 to $400,000. The council tabled it until December 14 pending written answers on site location, floodplain risk, fire response and corporate ownership.
Impact summary
If approved, the county would collect $400,000 a year for ten years from the solar-plus-storage project; without the amendment, the existing solar project proceeds but the storage component doesn't.
Applicant
- Name
- Worthington Solar, LLC (Kevin Ashram, Jerome Power representative; Nora Henning, development manager)
At a glance
- Hearings
- 2
- Public comments
- 0
- Total mentions
- 2
Last vote · County Commission
Discussed at 2 meetings in the last 60 days; most recently Nov 17, 2026.
Meeting timeline (2)
Greene County Commissioners — November 17, 2026
Geronimo Power wants to amend the solar project's economic development agreement to add a $50 million battery storage facility, trading 100% tax abatement for the first ten years for an extra $150,000 a year in county payments. Commissioners tabled it until the council acts in December.
Greene County Council — November 16, 2026
The company asked to amend its economic development agreement to add a battery energy storage component with $50 million in new investment, raising its annual payments to the county from $250,000 to $400,000. The council tabled it until December 14 pending written answers on site location, floodplain risk, fire response and corporate ownership.
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Greene County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.