Bridlewood Subdivision bond releases
The county engineer signed off on releasing nearly $91,000 in cash sureties for Bridlewood Subdivision Sections 2 and 3, with 25 percent maintenance bonds retained.
Edwardsville School Community Center READI 2.0 funding
Renovation estimates jumped $500,000, and replacing the old gym would add $916,000 more. The county signed a local match commitment letter to keep its $2.05 million in state READI 2.0 funding and stay in the running for new state money.
Edwardsville School gym demolition
The county is applying for a Lilly grant to help fund the gym remodel at the former Edwardsville School, now pushing $400,000, alongside a separate Aaron Howtons grant application for the rest of the facility.
County stance on data centers
A New Albany resident asked what the county's posture is now that data centers have appeared in New Albany. Commissioners said internal procedures exist for any new business, including data centers, and no moratorium is being considered.
Health department building funding shortfall
Renovation bids came in at $2.9 million against a $2.4 million target, leaving a roughly $962,000 gap. Both bodies committed up to $500,000 each in GO bond funds and directed staff to scrape together the rest, avoiding a new 20-year bond.
North Annex Blight Removal Grant
The Commissioners pitched a Community Project Funding grant to remove blight at the North Annex. Grant money could spare local tax dollars for demolition and cleanup.
Health and Human Services Center Construction Bids
The county opened construction bids for the new health center, which came in higher than the initial $2.4 million estimate, prompting review for responsiveness.