Civic Issues
Topics getting the most attention in Fishers public meetings, ranked by how frequently they are discussed.
13 issues in roads with high priority
Southeastern and Connecticut roundabout design
The city won funding in April for a new roundabout at Southeastern Parkway and Connecticut Road on the far east side, and HDR was picked from three firms to design it, handle right-of-way acquisition, and coordinate utilities. Design is the first step before construction.
116th Street storm sewer work for Maple Del Development
Maple Del Development needs to connect its storm sewer into the line under 116th Street, requiring a few days of road work — likely timed around school schedules to limit disruption. The developer pays for everything and repairs the road.
Pedestrian Crossing Time at E 116th Street
Residents noted 116th Street between Cumberland and Hoosier Road has seen two fatal accidents since October 2020 with a 40 mph limit, and questioned why no traffic study was required for this project. Commissioners discussed the planned Spyglass Falls signal and a possible roundabout.
Olio and Southeastern Roundabout Construction Timing
The busy roundabout gets rebuilt, plus a new stoplight near St. Vincent where left turns over the I-69 bridge have become dangerous. Most of the area stays open during construction with short detours.
Traffic fatalities and safety on 126th Street
Two residents died in a 2021 crash at 126th Street and Whisper Way when struck by a vehicle traveling 77 mph. Opponents demanded a traffic light, roundabout, or Michigan left before any commercial traffic is added; staff said engineering has studied a light and doesn't favor one at this site, and that traffic review comes later through TAC.
Trail detours and public transportation
A resident urged the council to diversify transportation options, arguing traffic concerns repeatedly threaten good infill projects and that about a third of Hoosiers cannot drive.
2027 Road Projects: Cumberland Road Widening and Resurfacing
Two INDOT contracts for the Cumberland Road project between 106th and 116th Street were extended to 2030 so they cover the full construction period, with most work happening in 2027.
116th Street and Allisonville Road intersection improvements
Good news if you dread that intersection: the planned roundabout has been scrapped in favor of longer turn and queuing lanes. Construction starts no earlier than March and should finish by October, with the road staying open the whole time.
Prairie Baptist Road condition and safety
A neighbor says Prairie Baptist Road is a worn, narrow old county road squeezed by detour traffic from the 126th and 136th Street projects, plus heavy fire and ambulance traffic from the new 106th Street-area station. He wants improvements sped up as this area develops. City staff say they've applied for federal MPO funding to improve the road and the 136th Street intersection, but it's a five-year process.
USA Parkway Widening
The road between USA Drive and the IKEA intersection is getting widened from 20 feet to 24 feet, phase one of a larger plan to widen all the way to 106th Street. Should ease congestion near the old Navigant building.
Streetlight Pre-Order for 131st and Brookschool Roundabout
Residents repeatedly described Brooks School Road as dangerous — a crest of a hill, narrow lanes, no shoulder, and a history of crashes near Breakwater. They demanded a full traffic study rather than the engineer's memo in the packet.
Road Resurfacing Contract 26-2 and INDOT Match
The city wants to put more Local Roads & Streets money into its budget. That money goes toward maintaining and improving city streets.
Thoroughfare Plan update
The city updates its road plan every year, and this version adds new intersection improvements and roundabouts — including several along the Brooks School Road corridor near Hamilton Proper, Sandstone Meadows, and Cottonwood Creek. It heads to City Council for final approval on March 16.