A construction-hours waiver letting the Citiview downtown project pour concrete at 5:30 a.m. for 11 remaining pours through August 10, then start framing at 6 a.m., with neighbor-notification commitments.
Impact summary
Downtown neighbors — especially at District South — will hear early-morning construction for the next several weeks, but the developer pledged notice, stipends, and resident meetings.
Applicant
- Name
- Rebar Development / TNH Construction
- Address
- Nickel Plate district, downtown Fishers
At a glance
- Hearings
- 1
- Public comments
- 2
- Total mentions
- 1
Last vote · Board of Public Works and Safety
Last discussed Jul 14, 2026.