SupportiveTomJul 14, 2026

Rebar Development's representative explained the heat-driven concrete challenge, the roughly $48,000 one-day ice cost, and outreach to the sole complainant, who will receive a stipend for noise-machine costs.

Board of Public Works and Safety - Jul 14, 2026 · 11:27 →
SupportiveZachJul 14, 2026

TNH Construction's Zach updated the pour schedule — 11 pours left through August 10 — and requested the 5:30 a.m. pour window plus a 6 a.m. start for framing and wall-panel deliveries.