Walnut Phase III project acceptance
Summary
The Walnut Phase III project got a paperwork fix with INDOT: 76 days of extension already granted for Milestone 1 now formally apply to Milestone 2 as well, at no additional cost.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Jun 25, 2026.
Impact analysis
None — it's a zero-sum change order, just extra days.
The project team and nearby residents get a realistic completion schedule without added expense.
Residents near the Walnut corridor may see the construction zone linger longer.
Mentions & discussions (3)
Board of Public Works - Jun 25, 2026
The Walnut Phase III project got a paperwork fix with INDOT: 76 days of extension already granted for Milestone 1 now formally apply to Milestone 2 as well, at no additional cost.
Board of Public Works - Jun 4, 2026
The board formally accepted the completed Walnut Phase III road project, which extends to Martin Luther King Jr. Boulevard.
Board of Public Works - May 7, 2026
The final change order on the Walnut Phase III project cut the contract by $1.52 million, bringing the total to about $20.45 million. That's real savings on a major road project.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Evansville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.