Lloyd Expressway/Cross Pointe Roundabout electrical relocation
Summary
The city is paying CenterPoint Energy $186,204.22 to relocate streetlights as part of the Cross Pointe roundabout project. A temporary drive will also keep nearby businesses accessible during construction.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Oct 1, 2026.
Impact analysis
Costs the city $186,204.22.
Drivers using the roundabout and nearby businesses that stay accessible during construction.
Mentions & discussions (3)
Evansville Tree Advisory Board - Oct 1, 2026
The board was scheduled to discuss coordinating with the Indiana Department of Transportation, likely regarding trees along state routes. State projects can affect street trees and plantings.
Board of Public Works - Jun 18, 2026
The city is paying CenterPoint Energy $186,204.22 to relocate streetlights as part of the Cross Pointe roundabout project. A temporary drive will also keep nearby businesses accessible during construction.
Board of Public Works - Apr 9, 2026
A $558,355.15 contract with SIGECON to move electric facilities along the Lloyd Expressway between Ingle Street and Wabash Avenue.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Evansville
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.