Cross Pointe roundabout change order
Summary
The roundabout project at Cross Pointe and Indiana got a $31,941.85 increase to use fast-curing concrete instead of temporary asphalt, keeping the project on track to finish this year — and should save about $50,000 overall.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 24, 2026.
Impact analysis
Contract grows by $31,941.85 now but is expected to net about $50,000 in savings.
Drivers using the roundabout get it finished sooner with less temporary traffic disruption.