AES Crossvine Solar / Battery Energy Storage System
Description
Residents asked the county to revoke or pause the solar permit and the battery storage system; after a lengthy review, Blessinger found no cause to revoke Permit 2024-02.
Impact summary
If revoked, the project — and its roughly $1.78 million a year in projected tax revenue — could be delayed or reshaped; residents worry about fire risk near schools and homes.
Applicant
- Name
- AES
- Address
- CR 750 South area, near Huntingburg
At a glance
- Hearings
- 2
- Public comments
- 1
- Total mentions
- 2
Last vote · County Commission
Last discussed Apr 6, 2026.
Meeting timeline (2)
County Commissioners — April 6, 2026
Residents asked the county to revoke or pause the solar permit and the battery storage system; after a lengthy review, Blessinger found no cause to revoke Permit 2024-02.
County Commissioners — March 16, 2026
Residents asked the commissioners to revoke Crossvine solar battery storage permit 2024-02, saying AES increased the battery count and had to resubmit to the state. Commissioners said they'd review before deciding.
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Dubois County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.