Venture One warehouse TIF bond and development agreement
Summary
A 1.2 million square foot warehouse/distribution center is planned east of I-65 between 101st and 109th Avenues, with a ~$100 million private investment. The Commission pledged 70% of the project's TIF revenue to repay up to $9.9 million in bonds funding public infrastructure — with no taxpayer backup and a projected 2038 payoff. The city retains 30% of the TIF for its own use.
At a glance
- Total mentions
- 4
- Last 30 days
- 0
Last discussed Apr 6, 2026.
Impact analysis
Up to $9.9 million in bonds repaid with 70% of the project's TIF revenue — no general taxpayer money on the hook, and the city keeps 30% of the TIF for its own use.
Residents gain jobs, local union labor opportunities, and improved infrastructure (roads, water, sewer) paid for by the project's own tax increment.
Some residents near I-65 corridors remain wary of more truck traffic and industrial growth in the area.
Mentions & discussions (4)
City Council (Regular) - Apr 6, 2026
The council finalized the financing package and development agreement for a 1.2-million-square-foot warehouse along I-65, expected to bring about 500 jobs. The developer buys its own bonds — no city debt — and there's no tax abatement.
Redevelopment Commission - Apr 6, 2026
A 135-acre development near 101st Street and the I-65/Mississippi extension moves forward. About $9.9 million in public infrastructure will be built, paid back through the tax revenue the project generates rather than the general budget.
City Council (Closed) - Mar 2, 2026
A 1,002,800 sq ft warehouse/distribution center (not a data center) along I-65 is moving forward on developer-purchased TIF bonds — no taxpayer repayment and no abatement — with a 70/30 TIF split that nets the city roughly $700K/year until 2038. Councilman Scott Evorik still dislikes the location but called the deal a good win.
Redevelopment Commission (Regular) - Mar 2, 2026
A 1.2 million square foot warehouse/distribution center is planned east of I-65 between 101st and 109th Avenues, with a ~$100 million private investment. The Commission pledged 70% of the project's TIF revenue to repay up to $9.9 million in bonds funding public infrastructure — with no taxpayer backup and a projected 2038 payoff. The city retains 30% of the TIF for its own use.
Related development
Venture One Crown Point LLC warehouse development agreement
A major jobs and construction project along the interstate, with no city debt; some council members debated whether the location is appropriate.
Venture One project
New construction jobs with a local labor agreement, plus upgraded roads, water and sewer around the site — paid for by the project's own TIF rather than the general taxpayer.
Venture One warehouse and distribution center TIF bond
City nets about $700K/year in TIF through 2038 and gets infrastructure improvements (intersection work, Mississippi extension, water/wastewater) without taxpayer-backed debt.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Crown Point
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.