The property covers 52% of its lot versus a 35% maximum, raising drainage questions near Gray Road. The city engineer found no 311 drainage complaints but the owners must still resolve on-site detention, possibly by paying into the thoroughfare fund or removing pavement.

At a glance

Total mentions
2
Last 30 days
1

Discussed at 1 meeting in the last 60 days; most recently Oct 26, 2026.