International Drive Extension with Jamestown
A new interlocal with Jamestown extends International Drive west to Darlington Street, linking N. Darlington Street and SR 75 with federal grant funding covering about 80%. The county fronts the 20% local match; the town pays back half and takes on maintenance.
Bridge 37 Rigid Deck Overlay Inspection
Ten county bridges are slated for HMA deck overlays — three bids were opened with Bum Gardner Asphalt lowest at $470,760.84, and a separate polymeric overlay contract with RAM Construction was approved for eight other bridges at $268,190.14.
All-way stop at CR 300 S and 500 E
A four-way stop is coming to a rural intersection with a history of crashes, following months of community push.
Boone Area Transit System Ridership Struggles
BATS runs 80-100 trips daily with 20 drivers and 20 vehicles, including daily school transport for an autistic student and dialysis trips to Carmel. Hiring is planned for late summer after several retirements, and two recalled vans are back on the lot.
Road projects and roundabout opening
Construction season is ramping up: a roundabout at 400 East and 100 South starts April 27 and will take about 150 days, plus resurfacing and striping projects across townships. Detours are posted on the county's Facebook page and website.
Highway department job title change
The county is investing in road maintenance: a brine system, a new road widener, a hotbox, bridge inspections, and a $417,974 structure replacement. The micro surfacing bids signal major road work coming this year.
400 South/100 South roundabout change orders
Two change orders adjust the roundabout project at 400 South and 100 South — a subgrade treatment change costing $81,394.36 and a $14,793.04 reduction as Lebanon supplies new lights.
300S/975E roundabout design agreement
After four years of chasing funding, the county is moving ahead with a roundabout at 300 South and 975 East. Most of the $863,700 design cost is covered by state and federal funds.
Countywide pavement data collection
The highway department will mount a sensor on a county vehicle to score every paved road, which helps win state road funding and documents conditions — including before the US 52 detour starts.
Speed hump policy
For the first time, subdivisions have a formal county policy for requesting speed humps — and for asking that they be removed. Schools and public safety get a say.
Speed Limit Reduction on John Martin Road
The commissioners finalized a speed limit change on John Martin Road, making it consistent on both ends of the county-controlled stretch. A new three-way stop nearby is under the city of Lebanon's control, so matching speeds improves safety near that intersection.