The county signed a road-project cost-share with Lebanon, got bridge deck overlays approved, and announced several closures — including a roundabout on CR 400 E/100 S through October and a full closure of SR 39 at the CSX tracks for about a week.
At a glance
- Total mentions
- 6
- Last 30 days
- 0
Last discussed Aug 3, 2026.
Impact analysis
Lebanon reimburses ~$255,523.56 of road work; bridge overlays cost up to $81,581 from bridge preservation funds.
Drivers get smoother roads and sturdier bridges — though detours will test patience this construction season.
Commuters face detours and closures on County Road 400 East, County Road 500 South, County Road 280 West, and State Road 39 over the coming months.
Mentions & discussions (6)
County Commissioners — August 3, 2026
A resident warned the commissioners that INDOT's passing-lane closure on SR 32 west sits in a curve where barrels are nearly invisible until drivers are right on them. She asked the county to press INDOT for a safer setup.
Commissioners Meeting Final — July 20, 2026
US 52 closes today between 300 North and 400 North through November, with detours via I-65 and State Road 47. County Road 100 East at 250 South closes about three days, County Road 50 East closes August 6 for water line work, and Middle Jamestown Road closes 45 days for a structure replacement.
Commissioners — June 15, 2026
INDOT will close all lanes of US 52 between 300 N and 400 N from on or after July 7 through October. The local detour uses 350 W and 250 N, and the county — not the state — pays to repair damage those roads take from heavy traffic.
Commissioners — June 1, 2026
A batch of closures begins this week: Wolfe Road at 750 South (through July 15), the North Park Street bridge for June, chip-and-seal work, plus INDOT bridge and I-65 fiber work with overnight lane closures.
Commissioners — May 18, 2026
Several closures: 300 South for bridge soil testing through May 22, Bridge 162 replacement on 500 South (about 130 days), plus state road and I-74 work — plan your routes.
Commissioners — May 4, 2026
The county signed a road-project cost-share with Lebanon, got bridge deck overlays approved, and announced several closures — including a roundabout on CR 400 E/100 S through October and a full closure of SR 39 at the CSX tracks for about a week.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Boone County
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.